CITYWIDE CONSTRUCTION PROJECTS


Project #14: Aldrich Road Reconstruction

Project Description: The City will be replacing water, sewer and drainage lines in this area.  Also part of the project will be streetscape improvements meant to deter speeding through the neighborhood.  The project is currently under construction and will completed in June or July.

Project Manager: Dave Desfosses 766-1411
Start Date: Ongoing
Estimated Time of Completion: Early July 2014
Funding Source: Local Bonding / Water / Sewer
Contractor: Lyman & Sons of Guilford NH

 