Islington Street Overnight Water Main Work begins Monday
June 28, 2019
On Monday, July 1st, overnight work on the water system will occur from approximately 4:30 PM to 7:00 AM Tuesday morning on Islington Street. Two crews will be working near the intersections of Jewell Court and Frenchman's Lane. Excavation of the water main at these locations will begin at approximately 6:00 PM in preparation to shut the water main down sometime after 11:15 PM. All properties affected by the water shutdown have received a notification flyer. Water service should be restored by 4:00 AM. The road should be free of any work by 7:00 AM. Police details and/or flaggers will be present to direct two-way alternating traffic around the work zones.
For more information on this work, please contact Ryan Flynn, Project Coordinator, at 603-766-1413.
This work is part of the Islington Street Corridor Improvements Project. For more information on this project, visit the project web page: https://bit.ly/2VH2F7j