Corporate Drive and Goosebay Drive Sewer Improvement Project
Content
The City of Portsmouth has a sewer improvement project that consists of the replacement of existing sewer pipes in Goosebay Drive and also in Corporate Drive from Rye Street to Goosebay Drive (see project area below). The City received bids in March and awarded the construction contract to Sargent Corporation of Stillwater, ME. Sargent Corporation has substantially completed the sewer improvements and only minor punch list items remain. This project is completed.
Project Update
Content
Upcoming Work
- Work is substantially complete and the contractor has demobilized.
- Punch list items remain to be completed. Final paving is anticipated to occur in the Spring of 2019.