Meetings
12.8.2022 Bartlett Street Public Information Meeting
December 12, 202212.8.2022 Bartlett Street Public Information Meeting
PROJECT UPDATE
Work is complete for the Bartlett Street project for the season except for installation of the bridge rail at the Hodgdon Brook culvert. The installation is tentatively scheduled for the week of December 16, 2024.
Work will resume in the Spring of 2025 to place the final pavement, roadway striping, raised crosswalk at Pine Street, raised intersection at Thornton Street, touch up the loam and re-seed.
The Morning Street scope of work is currently on HOLD and will be reevaluated in the Spring.
Project Description:
Bartlett Street Project Preconstruction Public Meeting, March 27, 2024
Go to the video of the meeting or the presentation link in the right-hand column of this page.
This project includes the reconstruction of underground public utilities (water, sewer, drainage) on Bartlett Street from Hodgdon Brook to Dennett Street, and Thornton Street from Woodbury Avenue to Bartlett Street. This will also include connections to existing utilities on side streets of Morning Street, Clinton Street, Pine Street, Meredith Way and Woodbury Ave. The project also consists of reconstructing the streetscape, including curbing, sidewalks, reconstructing the roadway and traffic calming measures.
Project Manager:
Marc Batchelder, Project Manager
603-766-1440
mrbatchelder@cityofportsmouth.com
Start: April 9, 2024
Estimated Completion: Substantial: November 2024 Final: June 2025
Estimated Cost: $4,600,000
Funding Source:
Design Engineer: Marc R. Batchelder, P.E. / In-House Staff
Construction Engineer: Altus Engineering, LLC
Contractor: Albanese D&S, Inc.
Following the December 9, 2022 meeting, the City is moving forward with further discussion on this design option.
For information on the Bartlett-Cate Street Intersection Project, visit this page.
12.8.2022 Bartlett Street Public Information Meeting