Willard Ave. Sewer
NOTICE: Orchard Street, Ash Street & Willard Ave. neighborhoods: EARLY TRASH PICKUP on Fridays. Trucks circulate on Fridays around 6:30 AM, now through the end of the Willard. Ave. construction project.
Willard road work will again require the closing of the outbound lane of Lafayette at the Willard-Lafayette intersection on Wed Nov 20, Thurs Nov 21 and Fri Nov 22, starting at 9 am each day. outbound traffic will be detoured onto Middle Road and then South Street.
Week of Nov 18: Road reconstruction work on Willard Ave. starting at 8 am. The contractor will be finishing up the gravel roadbed placement on Willard. The road will be closed to through traffic and not allow on-street parking. The City asks that residents please move vehicle(s) from the work zone area prior to 7 am. Effort will be made to limit the disruption to one day but may take longer than anticipated. Emergency access will be maintained throughout.
If you have any questions, the on-site contractor contact is John McCarthy, Resident Project Representative (603) 498-0298 or contact Zachary Cronin, Assistant City Engineer, at (603) 610-7304 or zmcronin@cityofportsmouth.com. For the April 17 Preconstruction meeting presentation and video recording, more information and to sign up for future email updates, on this page.
To receive project updates, subscribe here.
Project Description:
The Department of Public Works began the process of a sewer separation project in the Union Street area in the spring of 2022. Although only the Union Street area falls within the Consent Decree zone, residents in the adjacent Willard Avenue area have complained about sewer odors, so the City will address that issue by installing separate sewer and stormwater mains in this area at the same time. As part of the City’s Wastewater Master Plan and Long Term Control Plan, separating wastewater from stormwater is an ongoing responsibility under the Consent Decree agreement between the City of Portsmouth and the Environmental Protection Agency (EPA) and New Hampshire Department of Environmental Services (NHDES). The project involves the installation of three separate water mains: one for drinking water, one for wastewater and one for stormwater, along with reconstruction of the streets. The project will help reduce combined sewer overflows (CSOs) when the single pipe is flooded with stormwater in heavy rain events.
The City and its consultants are in the preliminary stages of design. Public meetings (Feb 2 and Jun 28) were held to inform Willard Avenue property owners about the project. The Consent Decree states that the sewer separation project must be substantially completed by October of 2023.
This project includes the reconstruction of the Willard Street area from Middle Street to Marston St. and includes Orchard St and Ash St. The replacement of sidewalks, pavement, and underground utilities including new storm drains, sanitary sewers and water mains are all a part of the project.
Final design continues on and will be complete near the end of 2023.
This project is part of the City’s continued sewer separation to reduce combined sewer overflows.
Project Status: 85% design complete. Construction anticipated in 2024.
Project Manager:
Zachary Cronin, Assistant City Engineer
603-610-7304 or 603-957-8795
zmcronin@cityofportsmouth.com
Estimated Completion:
Estimated Cost:
Funding Source: Funding anticipated from Sewer System Upgrade bonding (CIP FY24-29 p. 56)
Designer/Contractor: CMA Engineers, Inc.
APR 17, 2024 Preconstruction Meeting: Go to the video recording of the meeting. Go to a PDF of the meeting presentation.
JUN 28, 2022. Go to video recording of the meeting. Go to a PDF of the presentation.
Detailed map of utilities layout.
Detailed map of proposed road and sidewalk configuration.
FEB 2, 2022 – Willard Avenue Area Sewer Separation Project
Revised map of Orchard Street:.
City staff and the project design consultant CMA Engineers shared details on the project and solicited residents’ thoughts on project requirements and opportunities. The meetings included a review of the existing site conditions, contemplated improvements, the design schedule, and a question and answer period. Future public meetings will address the proposed design approach and overall construction timeline.
Through February, the City and its subcontractors surveyed homes and buildings in the area to determine the location and elevation of sewer service pipes from each building. This review ensures that the new sewer main accommodates these outflows properly. The City is working with CMA Engineers (Portsmouth, NH) and Flow Assessment (Auburn, NH) to conduct those surveys and asks for your cooperation and assistance.