Fleet Street Sewer Separation
The sewer separation project on Fleet Street is required through the City's Long Term Control Plan and Supplemental Compliance Plan. The project includes water, sewer, drainage upgrades along with full streetscape rework and other pedestrian enhancements. Funding for this work will come from the Water and Sewer Enterprise Funds and the General Fund.
Given the scope of this project, it will need to be completed in phases: Phase 1, a new drain line from the North Mill Pond; Phase 2, work in the Vaughan Mall and upper Congress Street area and Phase 3 on Fleet Street from Hanover Street to Court Street as well as a potential expansion of the project limits as determined during the design.
Update July 2024
Phase 1: Wetland permits submitted for work on outflow at North Mill Pond.
Phase 2: Underwood working on the design for Vaughan Mall and Congress Street.
Phase 3: Fleet Street Redesign